Gigaclear email: 15th December 2015, Programme of Work

posted 16 Dec 2015, 03:06 by David Carlisle

Further to our meeting [with Souldern Parish Council] on Friday please see below points raised:

 

·         Works to begin on High street at Wharf Lane end on Wed 16th December and work back towards centre of High street

·         Gang working on Foxhill Lane should emerge onto High street also and work in front of 1st crew.

·         All excavations to be completed by 18th December and reinstatement of all live works to be completed by 21st

·         All spoil and barriers, works to be closed down 21st December and re-starting on Monday 4th January

·         Aim to complete all works beginning of February

·         When working , crews will endeavour to maintain access wherever possible.Please feel free to discuss any access issues with crews directly or contact myself.

·         Where possible all trenches will be permanently reinstated the same day, where this is not  possible it will be the following day and any excavations will be barriered off.

·         We will make sure that where there are risks to existing stone walls we will investigate relocating routes, however you will be covered under our public liability if our works directly undermine or damage structures.

·         We are happy to discuss the siting of pots if once it is marked you deem it not fit for purpose. This should be called in to our customer service team who can relay to our design team.

·         Gigaclear will carry out snagging visit on completion of all works , this will ensure all verge,highway and footway reinstatement are restored to their former state and to a standard deemed suitable by OCC Highways inspectors.

 

If you feel I have missed anything from our discussion please feel free to call me with any concerns.

 

Kind Regards,

 

David Thrower |Project Manager  
Gigaclear plc